Contract Agreement Amount

Rs. 1,15,79,410

Physical Progress

15.00%

Financial Progress

12.80%

Remaining Payment

Rs. 87

Road Improvement Works along Barahathwa-3 Bhagwatipur dekhi paschim Nimtol Sadak (approach road at Budhi Bagmati), Sarlahi

Office: हेभिईक्युपमेन्ट डिभिजन, कैलाली (42)

Fiscal Year: 079-80

15.00%

Contract Date: 4-May-23

Start Date: 4-May-23

Completion Date: 30-Jun-2024 (EOT Done)

Project Description

No description available.