Contract Agreement Amount
Rs. 71,51,518
Physical Progress
9.10%
Financial Progress
12.55%
Remaining Payment
Rs. 87
Construction of Basantapur - Hattifarsaatikar - kaanchhibazaar - Ganeshnagar Road and Rigid Pavement at intersection Chowk of Bhumahi - Parasi and Parasi - Narayanchowk
Office: सडक डिभिजन, वुटवल (28)
Fiscal Year: 076-77
Contract Date: 17-Nov-19
Start Date: 17-Nov-19
Completion Date: 17-May-2020 (EOT Not Done)
Project Description
No description available.