Contract Agreement Amount
Rs. 8,00,12,214
Physical Progress
15.00%
Financial Progress
12.54%
Remaining Payment
Rs. 87
Construction of PSC Girder Bridge (2x40m span) over Dhad Molung Khola along Madhavpur-Sisneri Road, Okhaldhunga
Office: डिभिजन सडक कार्यालय, हर्कपुर, ओखलढुङगा (175)
Fiscal Year: 076-77
Contract Date: 16-Dec-20
Start Date: 23-Dec-20
Completion Date: 11-Jun-2023 (EOT Not Done)
Project Description
No description available.