Contract Agreement Amount

Rs. 1,25,77,645

Physical Progress

30.00%

Financial Progress

12.53%

Remaining Payment

Rs. 87

Structural and Surface dressing Works on Siddhartha Highway(Jhumsa-Kerabari section)

Office: सडक डिभिजन, पाल्पा (27)

Fiscal Year: 078-79

30.00%

Contract Date: 8-Feb-22

Start Date: 22-Feb-22

Completion Date: 09-Jul-2022 (EOT Not Done)

Project Description

No description available.