Contract Agreement Amount
Rs. 95,08,321
Physical Progress
15.00%
Financial Progress
12.07%
Remaining Payment
Rs. 87
Specific Maintenance Works at Mahendra Highway (Kakarbhitta - Mawa Seciton) Road, Jhapa
Office: डिभिजन सडक कार्यालय, झापा (13)
Fiscal Year: 076-77
Contract Date: 20-Dec-19
Start Date: 20-Dec-19
Completion Date: 29-Jun-2020 (EOT Not Done)