Contract Agreement Amount

Rs. 23,21,650

Physical Progress

11.00%

Financial Progress

11.77%

Remaining Payment

Rs. 88

Road Construction Works along Sunaulomarg Drain along With Blacktop

Office: डिभिजन सडक कार्यालय, मोरङ (14)

Fiscal Year: 078-79

11.00%

Contract Date: 31-May-22

Start Date: 31-May-22

Completion Date: 12-Jan-2023 (EOT Done)

Project Description

No description available.