Contract Agreement Amount

Rs. 8,40,45,145

Physical Progress

12.00%

Financial Progress

11.22%

Remaining Payment

Rs. 88

Roadway Excavation, Construction of Drain and Structure, Hume Pipe Culverts upto Blacktop standard along Chisapani-Dakaha-Chakmake-Bahun Tilping-Chandibhanjyang-Nawalpur Ghat-Palapu (25+500 to 30+500)

Office: डिभिजन सडक कार्यालय, खुर्कोट (185)

Fiscal Year: 078-79

12.00%

Contract Date: 4-Mar-22

Start Date: 4-Mar-22

Completion Date: 03-Jul-2024 (EOT Not Done)

Project Description

No description available.