Contract Agreement Amount
Rs. 5,80,14,439
Physical Progress
12.00%
Financial Progress
11.11%
Remaining Payment
Rs. 88
Roadway Excavation and Structural works on Sworna Sagarmatha Brihat Chakrapath Road (Barkhughat to Sukepokhari), Solukhumbhu.
Office: डिभिजन सडक कार्यालय, चितवन (20)
Fiscal Year: 078-79
Contract Date: 1-Jul-22
Start Date: 1-Jul-22
Completion Date: 01-Jan-2024 (EOT Not Done)
Project Description
No description available.