Contract Agreement Amount

Rs. 5,80,14,439

Physical Progress

12.00%

Financial Progress

11.11%

Remaining Payment

Rs. 88

Roadway Excavation and Structural works on Sworna Sagarmatha Brihat Chakrapath Road (Barkhughat to Sukepokhari), Solukhumbhu.

Office: डिभिजन सडक कार्यालय, चितवन (20)

Fiscal Year: 078-79

12.00%

Contract Date: 1-Jul-22

Start Date: 1-Jul-22

Completion Date: 01-Jan-2024 (EOT Not Done)

Project Description

No description available.