Contract Agreement Amount

Rs. 47,17,145

Physical Progress

10.94%

Financial Progress

10.73%

Remaining Payment

Rs. 89

Recurrent Maintenance work along Mawa Khola to Itahari (MRM) section

Office: डिभिजन सडक कार्यालय, मोरङ (14)

Fiscal Year: 079-80

10.94%

Contract Date: 21-Aug-22

Start Date: 22-Aug-22

Completion Date: 15-Dec-2022 (EOT Not Done)

Project Description

No description available.