Contract Agreement Amount
Rs. 5,21,12,609
Physical Progress
100.00%
Financial Progress
10.64%
Remaining Payment
Rs. 89
Construction of RCC Bridge over Maleriya Nala on Chadani Dodara Na.Pa.3,Pipalchautara Road, Kanchanpur
Office: सडक डिभिजन, कञ्चनपुर (34)
Fiscal Year: 073-74
Contract Date: 24-May-17
Start Date: 24-May-17
Completion Date: 25-Nov-2020 (EOT Done)
Project Description
No description available.