Contract Agreement Amount

Rs. 1,67,82,293

Physical Progress

11.00%

Financial Progress

10.48%

Remaining Payment

Rs. 89

Road improvement works on Chhinchu-jajarkot Road

Office: सडक डिभिजन, सुर्खेत (33)

Fiscal Year: 077-78

11.00%

Contract Date: 23-Feb-21

Start Date: 2-Mar-21

Completion Date: 04-Jul-2021 (EOT Not Done)

Project Description

No description available.