Contract Agreement Amount
Rs. 1,67,82,293
Physical Progress
11.00%
Financial Progress
10.48%
Remaining Payment
Rs. 89
Road improvement works on Chhinchu-jajarkot Road
Office: सडक डिभिजन, सुर्खेत (33)
Fiscal Year: 077-78
Contract Date: 23-Feb-21
Start Date: 2-Mar-21
Completion Date: 04-Jul-2021 (EOT Not Done)
Project Description
No description available.