Contract Agreement Amount

Rs. 4,25,04,060

Physical Progress

3.00%

Financial Progress

10.08%

Remaining Payment

Rs. 89

Road Rehabilitation and Widening Work along Karnali Highway, (Sherighat-Manma Section) at ch 143+000 to 150+000, Kalikot (RDJML/33701138/078/79-02)

Office: डिभिजन सडक कार्यालय, जुम्ला (179)

Fiscal Year: 078-79

3.00%

Contract Date: 4-Jul-21

Start Date: 4-Jul-21

Completion Date: 02-Oct-2021 (EOT Not Done)

Project Description

No description available.