Contract Agreement Amount
Rs. 1,07,31,00,000
Physical Progress
0.00%
Financial Progress
10.00%
Remaining Payment
Rs. 90
Design and Build of Madi River Bridge
Office: Unknown (1)
Fiscal Year:
Contract Date: 11-Aug-22
Start Date: 11-Aug-22
Completion Date: 10-Aug-2025 (EOT Not Done)
Project Description
No description available.