Contract Agreement Amount

Rs. 2,19,25,913

Physical Progress

0.00%

Financial Progress

0.00%

Remaining Payment

Rs. 100

Construction of Bridge over Thali Brigde along Bariyapur-Paterwa Road,Bara

Office: हुलाकी राजमार्ग आयोजना, योजना कार्यालय, वीरगंज, पर्सा (168)

Fiscal Year: 068-69

0.00%

Contract Date: 13-Jul-11

Start Date: 13-Jul-11

Completion Date: 12-Jul-2013 (EOT Not Done)

Project Description

No description available.