Contract Agreement Amount
Rs. 2,19,25,913
Physical Progress
0.00%
Financial Progress
0.00%
Remaining Payment
Rs. 100
Construction of Bridge over Thali Brigde along Bariyapur-Paterwa Road,Bara
Office: हुलाकी राजमार्ग आयोजना, योजना कार्यालय, वीरगंज, पर्सा (168)
Fiscal Year: 068-69
Contract Date: 13-Jul-11
Start Date: 13-Jul-11
Completion Date: 12-Jul-2013 (EOT Not Done)
Project Description
No description available.