Contract Agreement Amount
Rs. 12,15,00,322
Physical Progress
7.00%
Financial Progress
6.54%
Remaining Payment
Rs. 93
Upgrading of Existing Earthen road to blacktop standard along Inarwa Malhaniya Phulbariya Banarjhulla Sagharachouk Tariya Lakkar Sakhuwa Maran Naraha Nathpatti Taratole Yadukuha
Office: सडक डिभिजन, पोखरा (26)
Fiscal Year: 078-79
Contract Date: 24-Jun-22
Start Date: 24-Jun-22
Completion Date: 08-Jul-2024 (EOT Not Done)
Project Description
No description available.