Contract Agreement Amount

Rs. 12,15,00,322

Physical Progress

7.00%

Financial Progress

6.54%

Remaining Payment

Rs. 93

Upgrading of Existing Earthen road to blacktop standard along Inarwa Malhaniya Phulbariya Banarjhulla Sagharachouk Tariya Lakkar Sakhuwa Maran Naraha Nathpatti Taratole Yadukuha

Office: सडक डिभिजन, पोखरा (26)

Fiscal Year: 078-79

7.00%

Contract Date: 24-Jun-22

Start Date: 24-Jun-22

Completion Date: 08-Jul-2024 (EOT Not Done)

Project Description

No description available.