Contract Agreement Amount
Rs. 58,94,800
Physical Progress
60.00%
Financial Progress
5.80%
Remaining Payment
Rs. 94
Excavation of Roadway and Structural works on Dumre- Bhaisikatta- Sardewa road section
Office: सडक डिभिजन, पाल्पा (27)
Fiscal Year: 078-79
Contract Date: 20-Jan-22
Start Date: 3-Feb-22
Completion Date: 09-Jul-2022 (EOT Not Done)
Project Description
No description available.