Contract Agreement Amount

Rs. 2,89,38,506

Physical Progress

15.00%

Financial Progress

4.94%

Remaining Payment

Rs. 95

Periodic Maintenance works at Mid Hill Highway NH 03 (Seti Highway) CH 32+000 to 50+000

Office: सडक डिभिजन, तनहुं (25)

Fiscal Year: 078-79

15.00%

Contract Date: 28-Oct-21

Start Date: 28-Oct-21

Completion Date: 13-May-2022 (EOT Not Done)

Project Description

No description available.