Contract Agreement Amount
Rs. 44,63,88,034
Physical Progress
5.00%
Financial Progress
4.40%
Remaining Payment
Rs. 95
Construction of road along Tinau River Corridor-India Boarder Road(Danav Section), Rupandehi (Chainage-0+000 to 2+480, 4+290 to 9+500 at right bank and 4+290 to 5+500 at left bank of Danav River)
Office: हेभिईक्युपमेन्ट डिभिजन, सुनसरी (37)
Fiscal Year: 077-78
Contract Date: 7-Mar-22
Start Date: 7-Mar-22
Completion Date: 08-Nov-2024 (EOT Not Done)