Contract Agreement Amount

Rs. 7,24,88,051

Physical Progress

2.00%

Financial Progress

1.83%

Remaining Payment

Rs. 98

Construction Road Track Open, Cross Drainage and Retaining Structure works of Arun Corridor Road

Office: योजना तथा अनुगमन महाशाखा (भूवातावरण तथा सामाजिक शाखा) (4)

Fiscal Year: 079-80

2.00%

Contract Date: 24-Dec-23

Start Date: 24-Dec-23

Completion Date: 21-Mar-2025 (EOT Not Done)

Project Description

No description available.