Contract Agreement Amount

Rs. 13,87,78,732

Physical Progress

0.00%

Financial Progress

1.80%

Remaining Payment

Rs. 98

Slope Stabilization and Protection for Road Slope Disaster Management of Tirtire Bhir Landslide, Nuwakot (Ch. 32+200)

Office: गल्छी त्रिशुली मैलुङ्ग स्याफ्रुवेशी रसुवागढी सडक योजना, विदुर नुवाकोट (83)

Fiscal Year: 076-77

0.00%

Contract Date: 9-Mar-21

Start Date: 23-Mar-21

Completion Date: 08-Mar-2023 (EOT Not Done)

Project Description

No description available.