Contract Agreement Amount

Rs. 50,27,87,285

Physical Progress

5.00%

Financial Progress

1.62%

Remaining Payment

Rs. 98

Upgrading of Inaruwa-Kaptangunj Road Sunsari

Office: योजना तथा अनुगमन महाशाखा (योजना अनुगमन तथा मुल्यांकन शाखा) (3)

Fiscal Year: 077-78

5.00%

Contract Date: 16-Jan-22

Start Date: 31-Jan-22

Completion Date: 19-Jul-2024 (EOT Not Done)

Project Description

No description available.