Contract Agreement Amount
Rs. 17,28,47,818
Physical Progress
1.70%
Financial Progress
1.33%
Remaining Payment
Rs. 98
Roadway cutting & structural works on Martadi-Ghatmuna-Seyadhunga-Dahakot Road Section Connecting Bajhang Border
Office: डिभिजन सडक कार्यालय, साँफेवगर, अछाम (178)
Fiscal Year: 078-79
Contract Date: 5-Jun-22
Start Date: 5-Jun-22
Completion Date: 04-Jun-2025 (EOT Not Done)