Contract Agreement Amount
Rs. 1,04,02,50,000
Physical Progress
5.00%
Financial Progress
0.69%
Remaining Payment
Rs. 99
Design and Build of Bridge over Karnali River,Sankarighat pul (pradesh no 5 ra 7 jodne) Tikapur ward no. 2, Kailali,Kailali/Bardiya
Office: सडक डिभिजन, डोटी (35)
Fiscal Year: 078-79
Contract Date: 1-Jan-23
Start Date: 1-Jan-23
Completion Date: 02-Oct-2026 (EOT Not Done)
Project Description
No description available.