Contract Agreement Amount
Rs. 1,11,66,640
Physical Progress
0.00%
Financial Progress
0.00%
Remaining Payment
Rs. 100
periodic Maintenance works
Office: डिभिजन सडक कार्यालय, मकवानपुर (19)
Fiscal Year: 078-79
Contract Date: 7-Apr-22
Start Date: 7-Apr-22
Completion Date: 10-Jul-2022 (EOT Not Done)
Project Description
No description available.