Contract Agreement Amount

Rs. 37,46,630

Physical Progress

0.00%

Financial Progress

0.00%

Remaining Payment

Rs. 100

oadway Excavation with drain works, Structure, Pipe culverts & Gravelling works at Gorkha Jilla Gandaki Ga.Pa. 8 siurintar Dekhi Sahidlakhan Thapa Ga.Pa. Banauti Dovan Sadak,Gorkha. Budget Head : 337011694 Project Start Fiscal Year : 2079/80

Office: सुदुरपच्चिमाञ्चल क्षेत्रिय सडक निर्देशनालय, डोटी (11)

Fiscal Year: 079-80

0.00%

Contract Date: 9-Jan-23

Start Date: 9-Jan-23

Completion Date: 24-Jun-2023 (EOT Not Done)

Project Description

No description available.