Contract Agreement Amount

Rs. 50,82,399

Physical Progress

0.00%

Financial Progress

0.00%

Remaining Payment

Rs. 100

Upgrading and Rehabiliation of road in Satbanjh-Jhulaghat Section of Pushpalal Mid Hill Highway (NH-03)

Office: सडक डिभिजन, बैतडी (36)

Fiscal Year: 078-79

0.00%

Contract Date: 29-Oct-21

Start Date: 29-Oct-21

Completion Date: 13-Apr-2022 (EOT Not Done)

Project Description

No description available.