Contract Agreement Amount
Rs. 14,47,786
Physical Progress
0.00%
Financial Progress
0.00%
Remaining Payment
Rs. 100
Upgrading And Rehabilitation of Road By Constructing Side Drain in Gokuleshor-Khalanga Section (80+000-110+000)of Satbajh Thaktoli Darchula Tinker Road(NH66)
Office: सडक डिभिजन, बैतडी (36)
Fiscal Year: 077-78
Contract Date: 29-May-21
Start Date: 29-May-21
Completion Date: 01-Dec-2021 (EOT Not Done)