Contract Agreement Amount

Rs. 14,47,500

Physical Progress

0.00%

Financial Progress

0.00%

Remaining Payment

Rs. 100

Supply of Construction Material at Division Yard (Package 2)

Office: डिभिजन सडक कार्यालय, काठमाण्डौ (22)

Fiscal Year: 076-77

0.00%

Contract Date: 15-Dec-19

Start Date: 15-Dec-19

Completion Date: 14-Jan-2020 (EOT Not Done)