Contract Agreement Amount
Rs. 12,35,500
Physical Progress
0.00%
Financial Progress
0.00%
Remaining Payment
Rs. 100
Supply of Construction Material at Division Yard
Office: डिभिजन सडक कार्यालय, काठमाण्डौ (22)
Fiscal Year: 076-77
Contract Date: 25-Dec-19
Start Date: 25-Dec-19
Completion Date: 24-Jan-2020 (EOT Not Done)
Project Description
No description available.