Contract Agreement Amount
Rs. 16,46,254
Physical Progress
0.00%
Financial Progress
0.00%
Remaining Payment
Rs. 100
Roadway excavation, Cross Drainage work with Retaining Structure at Chhepetar Amalapani Lamagaun BeniKhola Belaute Jarebar Sadak Gorkha Na pa 5 9 ra 3 Gorkha.
Office: डिभिजन सडक कार्यालय, ईलाम (12)
Fiscal Year: 080-81
Contract Date: 9-Nov-23
Start Date: 9-Nov-23
Completion Date: 09-Jul-2024 (EOT Not Done)
Project Description
No description available.