Contract Agreement Amount

Rs. 20,70,04,384

Physical Progress

0.00%

Financial Progress

0.00%

Remaining Payment

Rs. 100

Roadway Upgrading / Excavation , Structural , Drainage and Pavement Works Along Shreekor-Sillegada-Kataujpaani-Rudreshwar-Dethala Road, Baitadi

Office: हेभिईक्युपमेन्ट डिभिजन, वांके (41)

Fiscal Year: 078-79

0.00%

Contract Date: 4-Sep-22

Start Date: 4-Sep-22

Completion Date: 03-May-2025 (EOT Not Done)

Project Description

No description available.