Contract Agreement Amount

Rs. 43,23,638

Physical Progress

0.00%

Financial Progress

0.00%

Remaining Payment

Rs. 100

Roadway Excavation,Masonary structure Gabion wall and cross drainage work on Dailekh-Lohore-Jufiya-Kandagaun-Charatha Road(ch8+000 to 20+000Kms)

Office: सडक डिभिजन, सुर्खेत (33)

Fiscal Year: 076-77

0.00%

Contract Date: 6-Nov-19

Start Date: 6-Nov-19

Completion Date: 12-Apr-2020 (EOT Not Done)

Project Description

No description available.