Contract Agreement Amount
Rs. 1,08,44,25,849
Physical Progress
0.00%
Financial Progress
0.00%
Remaining Payment
Rs. 100
Construction and Improvement of Nagdhunga-Naubise Section (Km 0+000 to 12+260) of Tribhuwan Highway
Office: Unknown (1)
Fiscal Year:
Contract Date: 12-Apr-22
Start Date: 12-Apr-22
Completion Date: 07-Jun-2024 (EOT Not Done)
Project Description
No description available.