Contract Agreement Amount
Rs. 36,04,281
Physical Progress
0.00%
Financial Progress
0.00%
Remaining Payment
Rs. 100
Roadway Excavation, Rcc Pavement Drainage works & Retaining Structure at Deulighat Ratmatay Mulabari Tilaram Bhanjyang kamalytar Bhotekotay Luitel Sadak, Gorkha.
Office: योजना तथा अनुगमन महाशाखा (योजना अनुगमन तथा मुल्यांकन शाखा) (3)
Fiscal Year: 080-81
Contract Date: 27-Nov-23
Start Date: 27-Nov-23
Completion Date: 09-Jul-2024 (EOT Not Done)
Project Description
No description available.