Contract Agreement Amount
Rs. 23,64,615
Physical Progress
0.00%
Financial Progress
0.00%
Remaining Payment
Rs. 100
Roadway Excavation, Hume pipe (NP3) and Structural Works on Saghutar Ghorakhori Okhaldunga Road , Okhaldunga
Office: मध्यपच्चिमाञ्चल क्षेत्रिय सडक निर्देशनालय,सुर्खेत (10)
Fiscal Year: 080-81
Contract Date: 9-Nov-23
Start Date: 9-Nov-23
Completion Date: 06-May-2024 (EOT Not Done)
Project Description
No description available.